clientAmar 1 Real Estate Investment Co.
consultantAECOM Middle East Limited
locationHIDD-KINGDOM OF BAHRAIN
General Description:
The project is being constructed by Great Lakes Dredge &
Dock and Nass Contracting.
The overall works in this project consists of forming the
landmass Phase 2 of Investment Gateway Bahrain for Amar
Real Estate. The landmass is protected with rockworks of
varying size and thickness dependent on the degree of
exposure of the fill. The reclamation material is to be taken
from a number of approved borrow areas defined in the
vicinity of the site.
The work is planned to be executed in 15months, consists of
approx. 2.75 million m2 of Reclamation area with Edge
Protection works of 5.40Km.